Snowy 2.0 cost blowout explodes in Senate as Dennis Barnes defends project and concedes major errors
Snowy Hydro chief executive Dennis Barnes has admitted the cost of Snowy 2.0 has blown out, saying "we got it wrong" during a Senate hearing. The revised target cost has risen to $22.2 billion, with an allowance for a $25 billion scenario, and full commissioning is now due in late 2029. Mr Barnes blamed poor design and missing scope, and said cancelling the project would make things worse. He also said the company will need government support by the middle of next year.