Snowy costs blow out but there's light at end of tunnel

Key points

  • The cost of Snowy 2.0, the Snowy Mountains hydro-electric expansion, may now reach up to $25 billion. The project was priced at $2 billion when proposed in 2017.
  • Its completion has been pushed back to late 2029. Energy Minister Chris Bowen says the project would still provide net benefits and blames geological challenges and early design decisions.
  • Tunnelling is now 65 per cent complete. Opposition energy spokesperson Dan Tehan has called for Mr Bowen to resign, which he has refused.
Snowy costs blow out but there's light at end of tunnel
Photo: PerthNow Local

Get local alerts + the full feed in the AU Now app

Alerts, Shorts and your saved stories — free on Google Play.

Get the app
Continue reading · PerthNow Local
Disclaimer

This is an AI-generated summary based on reporting by PerthNow Local. It may not reflect every detail of the original story exactly. Tap “Continue reading” above for the full, original article.

Follow this story in the AU Now app

Alerts for your suburb, Shorts and saved stories — free on Google Play.

Get the app

Advertise with AU Now →

Join the conversation

You can read freely. Sign in only to join the conversation.

Signing in on the website is coming soon. For now, use the AU Now app to like, comment, save and follow.

Get the app
MAKE IT LOCAL

Where should your news begin?

Choose your home area for nearby stories, weather and alerts.

Start typing to find your area.

Comments

…