Snowy Hydro 2.0 is costing $25bn – 12 times more than its initial estimate. How did we get here?
Key points
- The publicly owned Snowy 2.0 hydroelectricity project now carries an estimated cost of up to $25bn, far above its original figure of about $2bn. Announced in 2017 by then prime minister Malcolm Turnbull, it would link two Snowy reservoirs through lengthy tunnels to store power for periods of high demand.
- Early feasibility work put the cost between $5.4bn and $6.9bn, and a final investment decision followed before geological studies were complete.
- Tunnelling has been slowed by stuck machines and a worker strike, pushing completion to late 2029 with more than a third of tunnelling still ahead.
Get local alerts + the full feed in the AU Now app
Alerts, Shorts and your saved stories — free on Google Play.
Disclaimer
This is an AI-generated summary based on reporting by Guardian AU. It may not reflect every detail of the original story exactly. Tap “Continue reading” above for the full, original article.
Follow this story in the AU Now app
Alerts for your suburb, Shorts and saved stories — free on Google Play.
Comments
No comments yet — start the conversation.